Do not qualify a valve supplier from a certificate folder and a quotation alone. Start by confirming the legal entity, the real production route and one traceable order record. Then match certificates, tests and documentation to the exact valves you intend to buy.
A six-part qualification sequence
Identify the contracting entity
Match the company name on the licence, quotation, bank beneficiary, invoice and export documents. If production and export entities differ, ask for the relationship in writing.
Map the real production route
Separate in-house work from casting, machining, coating, actuator assembly and third-party testing. Outsourcing is not automatically a problem; hidden responsibility is.
Check certificate scope
Read the legal name, address, product scope, standard, issue date and expiry date. A valid ISO certificate does not prove that every proposed valve is certified.
Trace one actual order
Choose one finished valve and follow its tag, material record, drawing revision, pressure-test result, inspection photos and packing mark.
Define purchase controls
Put the approved data sheet, inspection points, document list, marking and packing requirements into the PO or an attached quality plan.
Close open points before deposit
Keep assumptions visible. Do not allow an unanswered material, dimension, test or document question to disappear inside a short commercial description.
Ask for records that can be cross-checked
A useful supplier pack is internally consistent. Names, addresses, standards and product scope should agree across the evidence.
- Business licence and contracting/export entity explanation
- Quality-system certificate and relevant product approvals
- Factory location, production flow and outsourced-process list
- Sample drawing, data sheet and bill-of-material structure
- Sample pressure-test or inspection record with traceable identification
- Calibration status for test gauges and measuring equipment
- Example nameplate, packaging mark and shipping document set
Red flags worth pausing for
- Bank beneficiary differs from the seller without explanation
- Certificates are cropped, unreadable or issued to another company
- Factory images cannot be linked to the named facility
- Test reports contain no model, size, pressure or traceable number
- The quotation uses broad wording such as “standard material”
- Critical subcontracting is denied first and disclosed later
- The supplier resists an agreed hold point or document list
A red flag is a reason to ask for evidence, not an automatic accusation. Record the answer and decide according to project risk.
Use a risk-based depth
| Purchase situation | Minimum check | Additional control |
|---|---|---|
| Catalogue stock item | Entity, specification, sample inspection and packing | Pre-shipment sampling for the first order |
| Project valve | Approved data sheet, drawing and inspection plan | Hold points, witness testing and document index |
| OEM/private label | Change control, marking, packaging and master sample | Pilot order and written nonconformity process |
How HSVA answers a qualification request
The Dongguan sales team organises the requested list in English and coordinates the response with the Nan’an production base. Where a document applies only to a specific product, order or manufacturing route, that scope should be stated rather than implied.